EN 1090-1:2009 + A1:2011 Chemisal were contacted in Jan 2018 by a global Medical Devices Company who required an urgent Facility to relocate a Recycling Function externally, in order to allow for relocation of equipment in the Production Plant. The only space available was a shipping area ramp, which had significant falls to allow for trailer access to shipping bays.

The Facility required adequate space for all three compactors, aisle space to allow movement of 1100 litre wheelies and be able to accommodate a desk and Filing cabinet. Sprinklers were required and electrically operated roller doors to allow large wheelies in and out in a single lane system.

Actions

  1. CHEMSAFE examined the requirements and reviewed the proposed location
  2. We developed a Proposal with detailed EN 1090 Compliant Solution
  3. The Design had an optimised traffic flow to ensure ease of use
  4. We produced a groundworks plan to ensure the internal floor was kept dry
  5. We also proposed a FAST Build Installation Schedule
  6. We reviewed the Site location in terms of safety, crane access and build feasibility

Outcome

  1. The Fast Build Proposal was accepted, and an Order was issued on Feb 1 2018
  2. Supplied groundworks plans, ground works were completed in two weeks
  3. Concrete was allowed to cure for a week
  4. Safety Documentation and Risk Assessment/ Method Statements delivered
  5. CHEMSAFE were on site Monday Feb 27 as agreed
  6. Works completed Tuesday Feb 28 at 3pm, and handed over
  7. Total time from Contact Order to handover was three weeks

Benefits

The CHEMSAFE QUICKBUILD Facility offers many benefits:

  • EN 1090 Compliant solution
  • Can be up to 9m wide, no supports required
  • Galvanised Steel for long life
  • Extremely fast solution, 3 to 4 weeks from contact if required urgently
  • Ready to go, just power the electrics
  • Facility is easily relocated or extended
  • Handed over ready for use
  • Cladding is Guaranteed for 20 Years
  • Lower costs, immediate solution when compared to Civil works

Client Comments

‘This was a challenging Project, especially in terms of timelines. A lot of activity had to follow on from delivery of the Recycling Facility on time, and this happened as they said. CHEMSAFE are very professional in terms of response, detail, and working with us on changes. Very impressive delivery!

POS, Project Lead

Initial Site

quikbuild facility project build03 

 
Initial Drawings below

quikbuild facility project build04 

 

Base in position

quikbuild facility project build05 

11am Day 1

quikbuild facility project build06 

4pm Day 1

quikbuild facility project build07 

5.30pm Day 1

quikbuild facility project build08 

11am Day 2

quikbuild facility project build09 

12.30pm Day 2

quikbuild facility project build10 

3.30pm Day 2 Completed

quikbuild facility project build11

quikbuild facility project build12 

 

CONTACT

  • Unit 9 Castletroy Park, Commercial Campus, Limerick, Ireland
  • T: + 353 (0)61 523 444
  • F: + 353 (0)61 523 2243
  • info@chemsafe.ie
  • M - F: 9am - 5pm

 

Our Shipping Partners:

Payment methods:

NEWSLETTER

Send me Exclusive Offers & Discounts!
Please wait